- A project has been defined to certain the following list of activities along with their required times of completion.
S/No. | Activity | Expected completion
time (weeks) |
Dependency |
1. | Require needs collection | 5 | – |
2. | Search design | 6 | 1 |
3. | Report design | 7 | 1 |
4. | Database design | 2 | 2, 3 |
5. | User documentation | 6 | 4 |
6. | Programming | 5 | 4 |
7. | Installation | 3 | 6 |
8. | Testing | 1 | 5, 7 |
- Draw a PERT chart of the activities
- Calculate the earliest expected completion time.
- Show the critical path.